In depth · Migration
Estimating an Access migration without getting it wrong
"It's a small database, it shouldn't take long." Many Access migration estimates start that way, and many end in overruns. The effort cannot be read from the file size or the number of users: it has to be measured, object by object.

Estimating a migration means answering a simple question: how much work does it take to get, in the new technology, an application that does what the current one does? The difficulty lies in "what the current one does". Until that has been measured, every estimate rests on an impression, and impressions are almost always wrong in the same direction: they underestimate.
Why estimates overrun

The safest way is to measure what the migration would weigh, object by object, from the application itself rather than from a walkthrough.
The gaps rarely come from misjudging what was seen. They come from what was not seen:
- Forms nobody showed you: the year-end process, the admin screen, the monthly import that only one person runs.
- Rules hidden in the code: a discount calculation, a numbering scheme, a consistency check placed on a "Before Update" event. They are invisible on screen, but their absence is noticed straight after the migration.
- External dependencies: tables linked to other files, Excel driven to produce spreadsheets, emails sent through Outlook, folders read on the network.
- Parts that are already broken: you discover during acceptance testing that a report stopped working long ago, and the question "should we rebuild it?" comes too late.
- The data itself: duplicates, dates stored as text, inconsistent values that the old application tolerated and the new one will reject.
Misleading indicators
| Commonly used indicator | Why it misleads |
|---|---|
| File size | It mostly reflects the volume of data. A small file can contain a very rich application; a large one, a single history table. |
| Number of users | It affects the target architecture, not the effort to rebuild. Three users can depend on a hundred forms. |
| Number of tables | Tables are the easiest part to migrate. The effort lies in forms, reports, queries and code. |
| Age of the application | An old application can be simple and clean; a recent one, built in a hurry, can be a tangle. |
What really drives the effort
The effort of a migration breaks down into a few families of work, each measurable in the existing application:
- Forms: how many, but above all how rich. A simple read-only form has nothing in common with a data-entry form with subforms, cascading lists and validation on every field.
- Reports: a printed report with groupings, subreports and calculations takes real work to reproduce, especially when it must stay identical to the document customers or authorities receive.
- Queries: select queries carry over well; action queries, crosstab queries and queries that call VBA functions need more care.
- VBA code: its volume and, above all, what it does. Code that merely opens forms disappears in a web application; code that carries business rules must be understood and then rewritten.
- Dependencies: every exchange with the outside world (files, Excel, email, other databases) is a small project in its own right.
- Data migration: cleansing, conversion, checks, then doing it all again at cut-over.
An object-by-object estimating method
The most reliable method starts from the application's actual inventory and estimates each object according to its complexity, rather than estimating "the application" in one go.
- Inventory every object: forms, reports, queries, modules, macros, tables, with their links.
- Set aside what is no longer used or no longer works, after agreeing it with users: that is work saved, provided the decision is made explicitly.
- Classify each remaining object into a complexity band, for example simple, medium or complex, using written criteria (number of fields, subforms, associated code, calculations).
- Assign a unit effort to each band, based on the experience of the team that will do the migration, ideally measured on a first batch.
- Add cross-cutting work: architecture, security, data migration, acceptance testing, training, cut-over.
- Apply a contingency proportionate to what remains uncertain, and show it as such.
This method has one decisive advantage: it makes the estimate open to challenge. Anyone can question how a form was classified or the unit effort for a band, and the estimate gets better. A lump-sum estimate cannot be discussed: you either believe it or you don't.
Contingency: where to put it and why
A contingency is not an admission of incompetence; it is an honest reflection of what is not yet known. It should be larger where the uncertainty is real:
- VBA code that could not be read in detail;
- external dependencies whose exact behaviour is not yet known;
- data quality, until a trial data migration has been run;
- forms whose rules have not been confirmed by users.
Conversely, a part that has already been measured (objects inventoried, working condition recorded, data analysed) calls for a small contingency. That is why a precise assessment reduces budget risk far more than it costs.
What a serious estimate should show
Whether the migration is done in-house or by a supplier, a credible estimate can be recognised by what it exposes. It should let you answer these questions:
- What inventory is it based on? The number of forms, reports, queries and modules taken into account, and the list of objects set aside.
- How was each object classified? The complexity grid used and how it was applied, object by object.
- What is counted separately? Data migration, external dependencies, security, acceptance testing, training, cut-over.
- Where are the contingencies, and why? An unexplained overall margin tells you nothing.
- What is not included? Written exclusions avoid misunderstandings at the end of the project.
An estimate that answers none of these questions is not necessarily wrong, but it cannot be checked. And an estimate that cannot be checked protects neither the client nor whoever proposes it.
Work in batches to correct the estimate as you go
Even the best method leaves some uncertainty. The safest way to reduce it is to migrate a representative batch first, for example a few forms from each band with their queries and code, then compare actual effort with planned effort. The gap measured on that first batch is used to correct the unit efforts for the rest. The estimate stops being a promise made once and for all; it becomes a management tool, updated with every batch.
Don't forget acceptance testing
Acceptance testing is the most frequently underestimated item. It means checking that the new application does what the old one did, on the same cases: same entries, same calculations, same reports. It needs users, who also have their day jobs, and it uncovers forgotten rules. Preparing test cases from the existing application, before the migration, makes this stage both faster and safer.
For the rest of the project, our guide Migrating an Access application: where to start describes the full approach, and Access to the web: the options helps you choose the target.
Read next: the four options for moving to the web.